Production Schedule


Production Schedule

Production Company: Tragic Daze Studios                            Date 01/10/13

Director: Martin Elesheku                                                 

Crew: Martin Elesheku, Andre George, (Peter) Quyen Nguyen, Johnny Barnes

                                       Details of Activities                                     Date:

Pre-production:

The Pitch - Crew                                                                                                                       

Proposal- Andre George                                                                                                          

Treatment- Martin Elesheku                                                                                                   

Audience profile- (Peter) Quyen Nguyen                                                                                             

Resources for Mise-en-scene - Andre George                                                                                          

Textual analysis- Crew (individual)                                                 

Risk Assessment - Johnny Barnes                                            

Screenplay- Martin Elesheku                                                                                                                    
Shot List-  Andre George & (Peter) Quyen Nguyen                                                                                                                   
Recce Report - Andre George  

Story Board - (Peter) Quyen Nguyen  

Film Review annotations - Andre George & Johnny Barnes

Film Review - Quyen Nguyen & Johnny Barnes

Posters- Martin Elesheku and Andre George and (Peter) Quyen Nguyen

Poster annotations- Martin Elesheku                                                                                                       
Titles and credits - (Peter) Quyen  Nguyen & Andre George                                                                                                                       

Production:

Filming days – 7th October, 8th October, 13th October, 14th October, 15th October, 20th October, 21st October, 22nd October                                                                                                               

Post-Production:                                                                                

Filming for Rough cut- 25th October                                                                                                        
Editing for rough cut – 7th October – 22nd October

Filming for Second Cut- 28th october-18th November

Editing for second cut- 19th November – 23rd November

Filming and editing for final cut-25th November- 7th December                                             

Final Cut Deadline: 7th December

Monday, 30 September 2013

Reece report


Reece report
The only location we will be using for our film is a house. We are using a house because it is typical for the horror genre. It provides a sense of security which we want to disrupt. The benefits of this location are that it will be available most of the time.
This is the living room. This is where most of the film will take place so it is vital that we get the spacing right so we have the right angles and framing.  As we are recording over different periods of time objects might move this could potentially break continuity. Furthermore lighting may be difficult as one of the lights are broken and the over isn’t very bright. To overcome this we will take pictures so we know what is where, we will also uses lamps to brighten up the room when necessary.



This is the kitchen. It is where the strange mishaps will start. It is the source of an important props it is also a good means to divert attention. It is good because it has good lighting. The kitchen is very small and so spacing for the camera will be tight. We will try to overcome this by making as much space as we can.